Procurement Products
Information Deliverables
G0000
Information required relating to supplier procurement, tender and appointment.
Elements
An Element Type is a component part of an Asset Type. Each Asset Type (except Asset Complex assets) will comprise of a prescribed set of Element Types. Some Element Types are essential and must be present to define an asset of that Asset Type. Other Element Types are optional, to be included when needed to define a particular Asset Type instance. An individual asset may have more than one instance of each Element Type.
This table lists the Element Types applicable to this Asset Type.
Element Type | Description | Element Code | Essential | Uniclass 2015 | Updates |
---|---|---|---|---|---|
G0100 Statement of Requirement | Document explaining the Employer's objectives and the scope of a package of work, including outputs, deliverables, delivery timescales, etc. | G01 | No | PM_10_20_82 | 11-04-2023 |
G0200 Tender | Tender Products. | G02 | No | PM_50_50_35 | 11-04-2023 |
G0300 Contract Scope or Works Information | Tender Products. | G03 | No | PM_50_50_15 | 11-04-2023 |
G0400 Tender Returns | Tender Products. | G04 | No | PM_50_50_60 | 11-04-2023 |
G0500 Clarifications | Tender Products. | G05 | No | PM_50_50_45 | 11-04-2023 |
G0800 Procurement Strategy | Document explaining how the Employer intends to procure products or services. | G08 | No | PM_50_50_01 | 11-04-2023 |
G1000 Contract Award Report | Report explaining the process used to procure a specific product or service, how the suppliers were evaluated and how the successful supplier was chosen. | G10 | No | PM_50_50_80 | 11-04-2023 |
G1100 Pain or Gain Share (if applicable) | Calculation of the Employer and Supplier pain or gain share, under Target Price contracts where Pain or Gain is applicable (e.g. NEC options C or D). | G11 | No | PM_55_55_85 | 11-04-2023 |
G1300 BIM Execution Plan | BIM Execution Plans, including Volume and Location Strategy. | G13 | No | PM_40_60_08 | 11-04-2023 |
G1400 Contract Agreements or Works Orders | Contracts agreed between the EA and Supplier that define the work to be carried out, and terms of payment. | G14 | No | PM_55_55_80 | 11-04-2023 |
G1500 Model Production and Delivery Table | Plan of what models are required throughout asset lifecycle, who will produce them, and to what LOD. See Appendix 1 of the CIC BIM Protocol for a sample. | G15 | No | PM_40_30_54 | 11-04-2023 |
G1900 Modelling Specification | Specification of modelling requirements for the geographic extent including specification for minimum acceptable detail and frequency of updates. | G19 | No | PM_40_30_55 | 11-04-2023 |
Attributes
An attribute is a particular piece of data that describes a property of an object. Each Asset Type is described by a different set of attributes, although there are some attributes that are common to many Asset Types.
The table below lists the attributes that are applicable to this Asset Type, along with the data profile requirements for each attribute and details of when and how each should be used and delivered.
Attribute | Format Details | Delivery | Purpose | Mandatory | geoCOBie Mapping | Updates |
---|