Site-based works
Information Deliverables
D0000
All information relating to the works carried out on site, including construction.
Elements
An Element Type is a component part of an Asset Type. Each Asset Type (except Asset Complex assets) will comprise of a prescribed set of Element Types. Some Element Types are essential and must be present to define an asset of that Asset Type. Other Element Types are optional, to be included when needed to define a particular Asset Type instance. An individual asset may have more than one instance of each Element Type.
This table lists the Element Types applicable to this Asset Type.
Element Type | Description | Element Code | Essential | Uniclass 2015 | Updates |
---|---|---|---|---|---|
D0100 Access and Traffic Management | Plans showing access to the site at all phases of the asset lifecycle with any phasing including any traffic management requirements. Includes access and traffic requirements during the construction phase, as well as access during operation and maintenance. | D01 | No | PM_60_10_50 | 11-04-2023 View history Request changes |
D0200 Setup or Prelim | Specific site holding, storage, accommodation and operations areas including any welfare facilities (on or off site). | D02 | No | PM_60_10_75 | 11-04-2023 View history Request changes |
D0300 Reinstatement | Proposals for post works reinstatement, plans, statements. | D03 | No | PM_60_20_15 | 11-04-2023 View history Request changes |
D0400 Tests, Inspections and Certification | Records of tests and inspections carried out, including site tests, manufacturers certification, etc. | D04 | No | PM_70 | 11-04-2023 View history Request changes |
D0500 Temporary Works | Proposals, designs and layout of temporary works from tender or during construction. | D05 | No | PM_60_10_85 | 11-04-2023 View history Request changes |
D0600 Contractors Technical Query | Contractors Technical Query. | D06 | No | PM_60_50_88 | 11-04-2023 View history Request changes |
D0700 Site Branding | Any site branding documents such as posters, information board, EA branding materials. | D07 | No | PM_60_10_55 | 11-04-2023 View history Request changes |
D0800 Site Supervisor Reports | Site supervisor's progress reports. | D08 | No | PM_60_30_66 | 11-04-2023 View history Request changes |
D0900 Defects or Snagging Records | Records of any defects identified post-construction works, including defect photographs. | D09 | No | PM_70_85_22 | 11-04-2023 View history Request changes |
D1000 Site Waste Management Plan | Site waste management plan. | D10 | No | PM_60_60_78 | 11-04-2023 View history Request changes |
D1100 Method Statements and Operating Procedures | Information on how tasks should be carried out. Covers whole lifecycle - construction tasks, maintenance tasks, operating tasks. | D11 | No | PM_60_20_22 | 11-04-2023 View history Request changes |
D1200 Record of Activities | For use in the operation phase: record of interventions, maintenance, operations, or inspection, etc. | D12 | No | PM_60_40_60 | 11-04-2023 View history Request changes |
D1300 Record of Cost and Carbon | For use in the operation phase: Record of the cost and carbon of interventions, maintenance, operation, etc. | D13 | No | PM_80_30_63 | 11-04-2023 View history Request changes |
D1400 Maintenance, Access, Risks and Hazards Schedule | A map based tool that allows Asset Performance and Field teams to set out access routes, hazards and other operational information. They contain sufficient detail to control hazards and manage risk. They are typically used to manage scheduled maintenance, work we do using the same method on a regular basis, such as grass cutting, weed cutting and general structure and channel maintenance. | D14 | No | PM_70_85_50 | 11-04-2023 View history Request changes |
D1500 Daily Diary | Used by Internal Deliverers to document daily activity on site. | D15 | No | PM_60_60_70 | 11-04-2023 View history Request changes |
D1600 Completion Records | Records of the completed works or maintenance. | D16 | No | PM_70_85 | 11-04-2023 View history Request changes |
D1700 MEICA PPM Schedule | PPM schedules are (electronic) documents detailing the tasks and other requirements to carry out the work safely. They are specified and attached to the templates. The schedules detail: - the tasks and the order in which they are to be carried out; - the major technical discipline required; - the frequency of the task; - generic SSoW and GRAs to be considered. Planning requirements are outlined as are any reporting documents. | D17 | No | PM_70_85_50 | 11-04-2023 View history Request changes |
Attributes
An attribute is a particular piece of data that describes a property of an object. Each Asset Type is described by a different set of attributes, although there are some attributes that are common to many Asset Types.
The table below lists the attributes that are applicable to this Asset Type, along with the data profile requirements for each attribute and details of when and how each should be used and delivered.
Attribute | Format Details | Delivery | Purpose | Mandatory | geoCOBie Mapping | Updates |
---|