Skip to main content

This is a new service – your feedback will help us to improve it.

Unit

Salcombe (Snapes Point to Splat Cove Point) 6C07

Summary management approach

Maintain/improve existing defences under a Hold The Line policy but do not build new defences along currently undefended sections under No Active Intervention, however proposals for a new 'Marine Hub' to be sited on the current Bacton Creek car park which may in turn require construction of new defences requires further consideration.

Generic approach assigned to this unit

Management approaches depend on funding and relevant approvals and permissions. Adaptation to coastal change may be needed. If defences are present, some risk from flooding, erosion or ground instability may remain.

Time periods (short (0 to 20 years), medium (20 to 50 years) and long (50 to 100)) are approximate and do not signify precise dates of management transitions.

0 to 20 years (2005 to 2025)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


20 to 50 years (2025 to 2055)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


50 to 100 years (2055 to 2105)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


Neighbouring units

The following units are within 1km of this one:

Protected sites

This area of coastline is not in or near a special protection area.

Data last updated: 2024-04-17

View Special Protection Area on the Data Services Platform

This area of coastline is in or near an area of outstanding natural beauty.

Data last updated: 2024-06-29

View Area of Outstanding Natural Beauty on the Data Services Platform

This area of coastline is in or near a special conservation area.

Data last updated: 2024-04-17

View Special Area of Conservation on the Data Services Platform

This area of coastline is not in or near a ramsar wetland area.

Data last updated: 2024-04-03

View Ramsar Site on the Data Services Platform

There is a scheduled monument near this area of coastline.

Data last updated: 2024-04-03

View Scheduled Monument on the Data Services Platform

This area of coastline is in or near a local nature reserve.

Data last updated: 2024-06-29

View Local Nature Reserve on the Data Services Platform

There are 2 sites of special scientific interest near this area of coastline.

Data last updated: 2024-08-31

View Site of Special Scientific Interest on the Data Services Platform

This area of coastline is not in or near a national nature reserve.

Data last updated: 2024-06-29

View National Nature Reserve on the Data Services Platform

There is a marine conservation zone near this area of coastline.

Data last updated: 2024-04-03

View Marine Conservation Zone on the Data Services Platform

Actions for this unit

All actions are subject to funding and approval, often by other parties than the Lead Organisation shown.

Reference NumberAction DescriptionAction Lead OrganisationAction Progress StatusPriority
16.176Develop Asset Management Plan to guide maintenance of defences and develop a programme of works in the Salcombe/Kingsbridge Estuary to ensure that they continue to provide adequate defence against the risk of flooding.Environment Agency / South Hams District CouncilNot yet startedMedium-low
16.182Explore plans and determine viability (including flood risk to new development) and potential to proceed regarding defecnes and potetnial loss of intertidal. Depending upon the outcome it may be necessary to ‘Revisit SMP Policy’ if the scheme is to proceed, which would include assessing the impacts of the proposed development on wider estuary functioning (physical and habitats).Pending agreementNot yet startedMedium-low
16.174Carry out a study to investigate the effects of Shoreline Management Plan policy on the heritage features at risk and consider mitigation measures and/or recording as appropriate.Pending agreementNot yet startedLow
16.177Quantify habitat losses and gains, and identify and secure sites to replace intertidal and freshwater habitat lost.Environment Agency / South Hams District CouncilNot yet startedLow

Download table as spreadsheet (CSV)

Download SMP documents

The information on this website represents the current SMP management approaches adopted by the local authorities within its area, and current actions needed to deliver them. These management approaches have been approved by the Environment Agency under its Strategic Overview for coastal flood and erosion risk management and are considered to be local policy.

The documents below provide the full SMP adopted locally and approved by the Environment Agency at the time of publication. Some of the information has changed in response to new government policy, new evidence or new work identified.

Data on this page

Main report

Appendices

Supporting Documents