West Cliff and Poole G.4

Summary management approach

Hold the Line of the existing seawall/promenade over the duration of the SMP to prevent coastal erosion of the base of the cliffs that rise landwards of this line. This will be achieved in the near term by recharge and sediment movement control which prevents exposure and risk of collapse of the aging seawall/promenade, and also sustains the significant recreational and amenity benefits along with defence of important infrastructure and properties along the crest of the cliff. There is a potential need to consider an Advance the Line approach at the target stage.

Generic approach assigned to this unit

Management approaches depend on funding and relevant approvals and permissions. Adaptation to coastal change may be needed. If defences are present, some risk from flooding, erosion or ground instability may remain.

Time periods (short (0 to 20 years), medium (20 to 50 years) and long (50 to 100)) are approximate and do not signify precise dates of management transitions.

0 to 20 years (2005 to 2025)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


20 to 50 years (2025 to 2055)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


50 to 100 years (2055 to 2105)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


Neighbouring units

The following units are within 1km of this one:

Protected sites

This area of coastline is in or near a special protection area.

Data last updated: 2024-04-17

View Special Protection Area on the Data Services Platform

This area of coastline is in or near an area of outstanding natural beauty.

Data last updated: 2024-06-29

View Area of Outstanding Natural Beauty on the Data Services Platform

This area of coastline is not in or near a special conservation area.

Data last updated: 2024-04-17

View Special Area of Conservation on the Data Services Platform

This area of coastline is not in or near a ramsar wetland area.

Data last updated: 2024-04-03

View Ramsar Site on the Data Services Platform

There are no scheduled monuments near this area of coastline.

Data last updated: 2024-04-03

View Scheduled Monument on the Data Services Platform

This area of coastline is in or near a local nature reserve.

Data last updated: 2024-06-29

View Local Nature Reserve on the Data Services Platform

There are 5 sites of special scientific interest near this area of coastline.

Data last updated: 2024-06-29

View Site of Special Scientific Interest on the Data Services Platform

This area of coastline is not in or near a national nature reserve.

Data last updated: 2024-06-29

View National Nature Reserve on the Data Services Platform

There are no marine conservation zones near this area of coastline.

Data last updated: 2024-04-03

View Marine Conservation Zone on the Data Services Platform

Actions for this unit

All actions are subject to funding and approval, often by other parties than the Lead Organisation shown.

Reference NumberAction DescriptionAction Lead OrganisationAction Progress StatusPriority
15.21Set-up a task and finish group to progress and implement actions arising from the SMP-Refresh covering units G.1 to G.4.Bournemouth, Christchurch and Poole CouncilCompleteMedium-high
15.39Deliver Poole Bay Beach Management Scheme Phase 2 and Phase 3Bournemouth, Christchurch and Poole CouncilProgressingMedium-high
15.40Deliver Poole Bay Beach Management Scheme Phase 4Bournemouth, Christchurch and Poole CouncilNot yet startedMedium-low

Download table as spreadsheet (CSV)

Download SMP documents

The information on this website represents the current SMP management approaches adopted by the local authorities within its area, and current actions needed to deliver them. These management approaches have been approved by the Environment Agency under its Strategic Overview for coastal flood and erosion risk management and are considered to be local policy.

The documents below provide the full SMP adopted locally and approved by the Environment Agency at the time of publication. Some of the information has changed in response to new government policy, new evidence or new work identified.

Data on this page

Main report

Appendices

Supporting Documents