Durlston Bay O.1
Summary management approach
Maintain the geological value through allowing natural coastal evolution. It is recognised that there will be property at risk in the medium to long term along the shoreline. Local activity to maintain or replace measures that address cliff slope drainage and limit cliff recession which have been installed in a localised section of this unit will not continue. This will ensure that the target of a more natural shoreline important to landscape and wildlife as part of the Jurassic Coast World Heritage Site can be achieved. As a consequence, there will be property at risk of being lost to erosion in the medium to long term.
Generic approach assigned to this unit
Management approaches depend on funding and relevant approvals and permissions. Adaptation to coastal change may be needed. If defences are present, some risk from flooding, erosion or ground instability may remain.
Time periods (short (0 to 20 years), medium (20 to 50 years) and long (50 to 100)) are approximate and do not signify precise dates of management transitions.
0 to 20 years (2005 to 2025)
MR6Managed realignmentLocal activity only
Where the overall intention is for a natural shoreline, not to encourage new defences. In some areas, where specified in the Shoreline Management Plan, works to repair or construct short stretches of defence to provide localised protection (such as to a slipway, access point or isolated properties) may be considered by the Local Planning Authority. All works require relevant permissions.
20 to 50 years (2025 to 2055)
MR6Managed realignmentLocal activity only
Where the overall intention is for a natural shoreline, not to encourage new defences. In some areas, where specified in the Shoreline Management Plan, works to repair or construct short stretches of defence to provide localised protection (such as to a slipway, access point or isolated properties) may be considered by the Local Planning Authority. All works require relevant permissions.
50 to 100 years (2055 to 2105)
NI2No active interventionDo not defend
Where no defences are present, and it would be technically, economically, or environmentally unsustainable to introduce defences due to their impact on other communities, or on sites protected for their environmental importance.
Neighbouring units
The following units are within 1km of this one:
Protected sites
This area of coastline is in or near a special protection area.
Data last updated: 2024-04-17
View Special Protection Area on the Data Services PlatformThis area of coastline is in or near an area of outstanding natural beauty.
Data last updated: 2024-06-29
View Area of Outstanding Natural Beauty on the Data Services PlatformThis area of coastline is in or near 2 special conservation areas.
Data last updated: 2024-04-17
View Special Area of Conservation on the Data Services PlatformThis area of coastline is not in or near a ramsar wetland area.
Data last updated: 2024-04-03
View Ramsar Site on the Data Services PlatformThere are no scheduled monuments near this area of coastline.
Data last updated: 2024-04-03
View Scheduled Monument on the Data Services PlatformThis area of coastline is in or near a local nature reserve.
Data last updated: 2024-06-29
View Local Nature Reserve on the Data Services PlatformThere is a site of special scientific interest near this area of coastline.
Data last updated: 2024-06-29
View Site of Special Scientific Interest on the Data Services PlatformThis area of coastline is in or near a national nature reserve.
Data last updated: 2024-06-29
View National Nature Reserve on the Data Services PlatformThere is a marine conservation zone near this area of coastline.
Data last updated: 2024-04-03
View Marine Conservation Zone on the Data Services PlatformActions for this unit
All actions are subject to funding and approval, often by other parties than the Lead Organisation shown.
Reference Number | Action Description | Action Lead Organisation | Action Progress Status | Priority |
---|---|---|---|---|
15.27 | Set-up a task and finish group to progress and implement actions arising from the SMP-Refresh covering units N.1 and O.1. | Bournemouth, Christchurch and Poole Council | Not yet started | Medium |
15.27.04 | Develop new North Swanage and Durlston Cliffs Management Strategy, ensuring ongoing engagement with the community, statutory stakeholders and private landowners is a key aspect of this work. | Dorset Council and National Trust | Not yet started | Medium |
15.48 | Ensure all SMP planning and delivery supports the Dorset and East Devon UNESCO World Heritage Site management policies and objectives as set out in the Jurassic Coast Partnership Plan. Engage with the Jurassic Coast Trust and affected stakeholders on the potential implications of risk management activities on the Site's Outstanding Universal Value, and any mitigation or compensation required. | Pending agreement | Progressing | Medium-low |
Download SMP documents
The information on this website represents the current SMP management approaches adopted by the local authorities within its area, and current actions needed to deliver them. These management approaches have been approved by the Environment Agency under its Strategic Overview for coastal flood and erosion risk management and are considered to be local policy.
The documents below provide the full SMP adopted locally and approved by the Environment Agency at the time of publication. Some of the information has changed in response to new government policy, new evidence or new work identified.
Data on this page
Main report
Appendices
- Appendix A - SMP Development
- Appendix B - Stakeholder Engagement
Appendix C - Baseline Process Understanding:
- Appendix D - Natural and Built Environment Baseline (Thematic Review)
- Appendix E - Issues and Objectives
- Appendix F - Strategic Environmental Assessment
- Appendix G - Scenario Testing
- Appendix H - Economics
- Appendix I - Estuary Assessment1
- Appendix J - Habitat Regulation Assessment
- Appendix K - Metadatabase
- Appendix L - Water Framework Directive
- Appendix M - Review of Hengistbury Head
- Appendix N - Client Steering Group Approvals