Rock 35.11

Summary management approach

Maintain defences in the short term from and including the existing defences to the east of the Sailing Club to the end of the coast protection structure at the start of Rock Dunes. In the medium to long term, the shoreline position will be moved to a more sustainable alignment. The short term defence maintenance will allow the important estuary access points and buildings associated with the RNLI and sailing and recreational activities to be moved to more sustainable positions in keeping with the agreed realignment option. This approach supports the SMP objectives of placing coastal communities, recreation and tourist facilities on a sustainable footing, while managing erosion and flood risks in a way that provides resilience to sea level rise and protects the natural environment.

Generic approach assigned to this unit

Management approaches depend on funding and relevant approvals and permissions. Adaptation to coastal change may be needed. If defences are present, some risk from flooding, erosion or ground instability may remain.

Time periods (short (0 to 20 years), medium (20 to 50 years) and long (50 to 100)) are approximate and do not signify precise dates of management transitions.

0 to 20 years (2005 to 2025)

HL3Hold the lineRepair not replace

Where protection is currently provided by coastal defence structures that might be maintained or repaired if funding allows, but not replaced if they fail or reach the end of their design life.


20 to 50 years (2025 to 2055)

MR7Managed realignmentPlaceholder

Managed realignment or defence activity may apply only to parts of this shoreline. The approach in this location may be especially dependent upon the outcome of further studies, economic assessments, the rate of coastal change or the actions of other asset owners affected by coastal change. As these become clearer, the management intention will be clarified.


50 to 100 years (2055 to 2105)

MR7Managed realignmentPlaceholder

Managed realignment or defence activity may apply only to parts of this shoreline. The approach in this location may be especially dependent upon the outcome of further studies, economic assessments, the rate of coastal change or the actions of other asset owners affected by coastal change. As these become clearer, the management intention will be clarified.


Neighbouring units

The following units are within 1km of this one:

Protected sites

This area of coastline is not in or near a special protection area.

Data last updated: 2024-04-17

View Special Protection Area on the Data Services Platform

This area of coastline is in or near an area of outstanding natural beauty.

Data last updated: 2024-06-29

View Area of Outstanding Natural Beauty on the Data Services Platform

This area of coastline is in or near a special conservation area.

Data last updated: 2024-04-17

View Special Area of Conservation on the Data Services Platform

This area of coastline is not in or near a ramsar wetland area.

Data last updated: 2024-04-03

View Ramsar Site on the Data Services Platform

There are no scheduled monuments near this area of coastline.

Data last updated: 2024-04-03

View Scheduled Monument on the Data Services Platform

This area of coastline is not in or near a local nature reserve.

Data last updated: 2024-06-29

View Local Nature Reserve on the Data Services Platform

There is a site of special scientific interest near this area of coastline.

Data last updated: 2024-06-29

View Site of Special Scientific Interest on the Data Services Platform

This area of coastline is not in or near a national nature reserve.

Data last updated: 2024-06-29

View National Nature Reserve on the Data Services Platform

There are 2 marine conservation zones near this area of coastline.

Data last updated: 2024-04-03

View Marine Conservation Zone on the Data Services Platform

Actions for this unit

All actions are subject to funding and approval, often by other parties than the Lead Organisation shown.

Reference NumberAction DescriptionAction Lead OrganisationAction Progress StatusPriority
17.150Develop a n adaptation plan for the areas impacted by managed realignment, potentially as part of a strategy for the entire Camel Estuary, underpinned by a better understanding of the whole behavioural system (informed by analysis of monitoring data) and impacts of management activities such as dredging.Pending agreementNot yet startedMedium

Download table as spreadsheet (CSV)

Download SMP documents

The information on this website represents the current SMP management approaches adopted by the local authorities within its area, and current actions needed to deliver them. These management approaches have been approved by the Environment Agency under its Strategic Overview for coastal flood and erosion risk management and are considered to be local policy.

The documents below provide the full SMP adopted locally and approved by the Environment Agency at the time of publication. Some of the information has changed in response to new government policy, new evidence or new work identified.

Data on this page

Main report

Appendices

Summaries

Supporting documents