Portmellon 8.5

Summary management approach

Repair defences in the short term to manage immediate storm damage impacts, on the basis that long term defence is not sustainable. During the 2020s, appraise options for re-alignment of highway and management of risks to property. The decision on future of highway will be key to how policy here is progressed. Identify potential environmental benefits of realignment to realise multiple benefits to the area from any change. Cornwall Council's recently adopted Climate Emergency Development Plan Document (Feb 2023) identifies Potmellon as a candidate location for adoption of a Coastal Change Management Area within Land Use Planning Policy. This in turn should support the coomunity to identify plans and opportunities to adapt their sewttlement.

Generic approach assigned to this unit

Management approaches depend on funding and relevant approvals and permissions. Adaptation to coastal change may be needed. If defences are present, some risk from flooding, erosion or ground instability may remain.

Time periods (short (0 to 20 years), medium (20 to 50 years) and long (50 to 100)) are approximate and do not signify precise dates of management transitions.

0 to 20 years (2005 to 2025)

HL3Hold the lineRepair not replace

Where protection is currently provided by coastal defence structures that might be maintained or repaired if funding allows, but not replaced if they fail or reach the end of their design life.


20 to 50 years (2025 to 2055)

MR7Managed realignmentPlaceholder

Managed realignment or defence activity may apply only to parts of this shoreline. The approach in this location may be especially dependent upon the outcome of further studies, economic assessments, the rate of coastal change or the actions of other asset owners affected by coastal change. As these become clearer, the management intention will be clarified.


50 to 100 years (2055 to 2105)

MR7Managed realignmentPlaceholder

Managed realignment or defence activity may apply only to parts of this shoreline. The approach in this location may be especially dependent upon the outcome of further studies, economic assessments, the rate of coastal change or the actions of other asset owners affected by coastal change. As these become clearer, the management intention will be clarified.


Neighbouring units

The following units are within 1km of this one:

Protected sites

This area of coastline is in or near a special protection area.

Data last updated: 2024-04-17

View Special Protection Area on the Data Services Platform

This area of coastline is in or near an area of outstanding natural beauty.

Data last updated: 2024-06-29

View Area of Outstanding Natural Beauty on the Data Services Platform

This area of coastline is in or near a special conservation area.

Data last updated: 2024-04-17

View Special Area of Conservation on the Data Services Platform

This area of coastline is not in or near a ramsar wetland area.

Data last updated: 2024-04-03

View Ramsar Site on the Data Services Platform

There are no scheduled monuments near this area of coastline.

Data last updated: 2024-04-03

View Scheduled Monument on the Data Services Platform

This area of coastline is not in or near a local nature reserve.

Data last updated: 2024-06-29

View Local Nature Reserve on the Data Services Platform

There are no sites of special scientific interest near this area of coastline.

Data last updated: 2024-06-29

View Site of Special Scientific Interest on the Data Services Platform

This area of coastline is not in or near a national nature reserve.

Data last updated: 2024-06-29

View National Nature Reserve on the Data Services Platform

There are no marine conservation zones near this area of coastline.

Data last updated: 2024-04-03

View Marine Conservation Zone on the Data Services Platform

Actions for this unit

All actions are subject to funding and approval, often by other parties than the Lead Organisation shown.

Reference NumberAction DescriptionAction Lead OrganisationAction Progress StatusPriority
17.033Develop an adaptation plan (supported by the Sustainable Coastal Communities project for the wider area). Ensure that the future flood risk implications to the community of not restoring the dunes as a more sustainable defence line, and the impact of the caravan park private defences on beach amenity, is communicated clearly as part of the ongoing engagement with the caravan park and wider community. Also clearly communicate the risks to the road if managed realignment is not implemented soon enough, and identify triggers for action. Ensure adaptation strategy included in Settlement strategy.Pending agreementNot yet startedMedium-low

Download table as spreadsheet (CSV)

Download SMP documents

The information on this website represents the current SMP management approaches adopted by the local authorities within its area, and current actions needed to deliver them. These management approaches have been approved by the Environment Agency under its Strategic Overview for coastal flood and erosion risk management and are considered to be local policy.

The documents below provide the full SMP adopted locally and approved by the Environment Agency at the time of publication. Some of the information has changed in response to new government policy, new evidence or new work identified.

Data on this page

Main report

Appendices

Summaries

Supporting documents