Skip to main content

This is a new service – your feedback will help us to improve it.

Unit

Castle Beach and Gyllyngvase 13.2

Summary management approach

Continue to defend the heavily developed shoreline, which brings important socio-economic benefits to the area. Pressures on the shoreline are light due to its sheltered nature, although some damage to Local Authority defences has been recorded in the last 5 years. Some coastal squeeze is likely to occur. This should not compromise the nature conservation features of the Fal & Helford Special Area of Conservation, as its boundary sits at mean low water, however inner boundary of the Special Protection Area sits at mean high water. therefore impacts will need to be monitored and future mitigation may need to include compensatory habitat.

Generic approach assigned to this unit

Management approaches depend on funding and relevant approvals and permissions. Adaptation to coastal change may be needed. If defences are present, some risk from flooding, erosion or ground instability may remain.

Time periods (short (0 to 20 years), medium (20 to 50 years) and long (50 to 100)) are approximate and do not signify precise dates of management transitions.

0 to 20 years (2005 to 2025)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


20 to 50 years (2025 to 2055)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


50 to 100 years (2055 to 2105)

HL1Hold the lineMaintain/replace

Where protection is currently provided by coastal defence structures or managed beaches, and the intention is to retain a defence along approximately the current alignment. This will involve replacing defences when needed. Defence type, method and standard of protection may be modified over time.


Neighbouring units

The following units are within 1km of this one:

Protected sites

This area of coastline is in or near a special protection area.

Data last updated: 2024-04-17

View Special Protection Area on the Data Services Platform

This area of coastline is in or near an area of outstanding natural beauty.

Data last updated: 2024-06-29

View Area of Outstanding Natural Beauty on the Data Services Platform

This area of coastline is in or near a special conservation area.

Data last updated: 2024-04-17

View Special Area of Conservation on the Data Services Platform

This area of coastline is not in or near a ramsar wetland area.

Data last updated: 2024-04-03

View Ramsar Site on the Data Services Platform

There is a scheduled monument near this area of coastline.

Data last updated: 2024-04-03

View Scheduled Monument on the Data Services Platform

This area of coastline is not in or near a local nature reserve.

Data last updated: 2024-06-29

View Local Nature Reserve on the Data Services Platform

There are no sites of special scientific interest near this area of coastline.

Data last updated: 2024-07-26

View Site of Special Scientific Interest on the Data Services Platform

This area of coastline is not in or near a national nature reserve.

Data last updated: 2024-06-29

View National Nature Reserve on the Data Services Platform

There are no marine conservation zones near this area of coastline.

Data last updated: 2024-04-03

View Marine Conservation Zone on the Data Services Platform

Actions for this unit

All actions are subject to funding and approval, often by other parties than the Lead Organisation shown.

Reference NumberAction DescriptionAction Lead OrganisationAction Progress StatusPriority
17.178Develop Fal and Helford Intertidal Habitat and Sedimentation Strategy. This should define sedimentation monitoring and other evidence requirements to improve understanding of evolution of Special Area of Conservation (SAC) features over the long term, maintain its condition and determine timescales for managed realignment. Develop an evidence base available for strategic planning and investment in risk management. Include a review of SAC boundary to include all mudflat and saltmarsh habitats at Mylor Creek, Navas, and Gweek Restronguet to Devoran, Tresillian, Penryn, Porth, Ruan Lanihorne, Truro - Upper Basin.Environment AgencyProgressingHigh

Download table as spreadsheet (CSV)

Download SMP documents

The information on this website represents the current SMP management approaches adopted by the local authorities within its area, and current actions needed to deliver them. These management approaches have been approved by the Environment Agency under its Strategic Overview for coastal flood and erosion risk management and are considered to be local policy.

The documents below provide the full SMP adopted locally and approved by the Environment Agency at the time of publication. Some of the information has changed in response to new government policy, new evidence or new work identified.

Data on this page

Main report

Appendices

Summaries

Supporting documents